Connection Order Matters: Path-Dependent Hosting Capacity in Distributed Generation Interconnection Queues
Williams Fernandes Fontinele, Pablo Torrez Caballero, Eduardo C. Marques Costa
SSRN Electronic Journal · 2026
Grid access queues for distributed generation (DG) are processed chronologically (FIFO) worldwide, assuming that connection order does not affect total accommodated capacity. Under high penetration this fails: each connection alters the feeder voltage profile, so the hosting capacity left for later projects is path-dependent and different orderings connect substantially different total power. Queue ordering is formulated as a sequential permutation problem with state-dependent feasibility: a parameter-free objective (maximize connected kW), hosting capacity updated by Newton-Raphson power flow after each decision, and a hybrid memetic algorithm (genetic algorithm with adaptive operator selection over three local-search neighborhoods).
On the IEEE 33-bus and 69-bus (Baran-Wu) networks across four penetration scenarios (46-499%): (i) path-dependence activates above about 120% penetration, below which all orderings are equivalent; (ii) optimized ordering connects on average 22.4% more power than FIFO on the 33-bus network (up to 67.6%; p < 0.001, Vargha-Delaney A = 1.0) and 9.7% more on the 69-bus (up to 17.3%), a topology-dependent mechanism; (iii) the driver is sequential evaluation with dynamic hosting capacity, not the metaheuristic: a multi-seed ablation over 9 configurations finds no significant difference from a GA-only variant (all p > 0.05). Bounding queue displacement to N/2 positions costs about 1% of total fitness. A paired Monte Carlo assessment (200 samples per instance) gives positive gains in 100% of samples wherever technical constraints are active; near the activation threshold the nominal gain is not robust.
Topology-aware sequencing can therefore increase DG accommodation within existing networks, grounding a revision of chronological interconnection policies.